State Kansas Where is the project? West of Salina, Kansas about 20 miles, and just north of Interstate 70 on both sides of Highway 14. The project is located in both Lincoln and Ellsworth Counties. What transmission line does the project connect with? Midwest Energy 230 kV transmission line in Ellsworth, County. What is the size of the project? 100.8 MW (Phase I) Phase II is an additional 150 MWs What turbines are being used? 1.8 MW V80 turbines manufactured by Vestas, with an 80-meter hub height and 80-meter blade diameter. Landowners and Acreage Involved Over 30 landowners and 12,000 acres are involved in the project. When did the project start operating? February 2008.